As some people in the Bennett Street area many have already noticed, a number of markings have recently appeared on the street. These are marking various utilities in preparation of a paving project set to begin around April 15th. This project will be done in three phases. The first phase will involve the installation of storm drains along the west side of Bennett Street from the area of 6337 Bennett to 6249 Bennett. The second phase is expected to begin in late May or the beginning of June, will involve the milling and repaving of Rasmussen Street, Bennett Street, Circle Drive, and Ridgewood Circle. Approximately one month after that, these same roads, along with Vick Street, Wayne Street, and Stanford Street will then be chip sealed. Please keep in mind that these dates are all tentative as they are weather dependent. Our Highway Superintendent, Kurt Allman, has advised he will be on site during these times and all area residents will be accommodated.
Barry VanNostrand
Town Supervisor